St. Paul Street
Update 5/30/2019 – St. Paul St is closed, signage is up directing pedestrian traffic from the parking
lot behind City Hall, along the west side of the building to use the front entrance. The electric portion
for new street lights are being installed followed by remaining concrete work. We will work to
maintain access to the utility drop box. To access the City Hall parking lot and St. Paul’s Church,
enter from Pleasant St.
Pleasant St – St. Paul to Walnut St
Update 5/30/2019 – The south side curb is anticipated to be poured starting today (5/30) with the
sidewalk and driveway aprons to follow and its anticipated that driveway access will be restored
early next week for the south side properties. The public sidewalk on north side will remain open
to pedestrian traffic during this time. After the sidewalk on the south side has cured, it will be opened
to the public and then the north side will be removed once St. Paul is open to traffic.