St. Paul Street
Update 5/23/2019 – St. Paul St is closed, signage is up directing pedestrian traffic from the parking
lot behind City Hall, along the west side of the building to use the front entrance. The electric portion
for new street lights will be installed after Memorial Day followed by remaining concrete work to be
completed. We will work to maintain access to the utility drop box. To access the parking lot and
St. Paul’s Church, enter from Pleasant St.
Pleasant St – St. Paul to Walnut St
Update 5/23/2019 – The south side curb is anticipated to be poured after Memorial Day with the
sidewalk and driveway aprons to follow. The public sidewalk on north side will remain open to
pedestrian traffic while the south side public sidewalk is being removed and replaced. After the
sidewalk on the south side has cured it will be opened to the public and then the north side will
be removed.
Pleasant St – Walnut St to Fowler St
Update 5/23/2019 – The concrete aprons to access your driveway will be cured and open for you to drive on starting today – Friday (5/24/2019).